Replace Chancery Generator and ATS

Design Build services to replace generator and associated electrical equipment and provide 15 minute FEBR Generator Enclosure.
  • Design Build services to Survey to inspect, assess, field verification of existing conditions
  • Develop and implement design
  • Submittals, Procurement, Warehousing
  • Shipping, coordination with post, local equipment vendor and COR.
  • Layout and construct new equipment pads
  • Coordination with local subs to prepare pad / provide concrete, and post. Strict security access requirements
  • Construction of weatherproof 15 minute FEBR enclosure with sound attenuation
  • FEBR doors, louvers, hardware
  • New compound diesel generator
  • Day tank / Fuel delivery System
  • ATS
  • Integral load bank
  • Controls
  • Arc Flash Study / Arc Flash labeling
  • Lights, outlets, subpanel
  • Fire alarm and Security
  • Extended Exhaust stack and ducting.
  • Electrical service, new Cable and Conduit
  • Replace breakers as needed throughout embassy compound
  • Surge Protection for ALL load panelboards throughout embassy compound
  • Sump pump and Drainage Control in main Electrical Room
  • Training, Testing and Commissioning.
  • Electrical Design – team with E.K. Fox to provide integrated design
  • Continual and open communications between all key stakeholders
  • Provide for a continuing level of operation of the Embassy missions critical functions during all construction periods
  • Prepare project manuals, bill of materials, quality control plan, construction schedules, construction cost estimates, and verify design/build costs.
  • Compliance with security requirements, CSP.
  • Prepare all required reports
  • Cleanup and Demobilization Project close-out documentation
Specific Trades Self Performed:
  • Project Administration/Management
  • Cost Estimating/Management
  • Design Coordination
  • CPM Schedule
  • Security Requirements
  • Submittals
  • Procurement
  • Shipping Logistics
  • Cost control
  • Required Reports
  • Quality Control
  • On Site Labor
  • Civil (local sub)
  • Carpentry
  • Electrical
  • Mechanical
  • Painting
  • Testing
  • Factory Certified Training and Commissioning
  • Project Closeout
Period of Performance:

Project award: 7/2016, Actual Completion: 7/2017 Originally Scheduled Completion Date: 6/2017

Completion date was extended due to delays in government design review as well as long lead times in manufacturing of the equipment. Project completed on time and within budget.
100% SELF PERFORMED
Due to the sensitive nature of the project, site plans and drawings are unavailable for presentation