Generator Set and Associated Electrical Equipment Replacement and PCC Fan Coil Upgrade

Design Build services to replace Critical load generator, Gear Package, and upgrade PCC air conditioning
  • Design Survey Architectural/ Mechanical/ Electrical Systems, Constructability, Security concerns
  • Electrical/Mechanical Design – team with E.K. Fox to provide integrated design
  • Continual and open communications between all key stakeholders
  • New 180 KW/225 KVA prime generator
  • ATS
  • AVR with internal step up transformer
  • Remote Control Panel
  • New day tank and fuel piping
  • Duct work
  • Critical grade muffler and exhaust piping
  • Demo existing equipment
  • New cassette fan coil units with heating coils
  • New piping and controls
  • New ceiling grid and tile
  • New 2×2 lighting.
  • Seismic supports
  • Designed hoist system to remove existing and deliver new equipment through available hatch.
  • Rigging of equipment to remove old and deliver new equipment to the space.
  • Shipping Logistics included special permits and local security personnel to arrange container delivery to facility.
  • Provide for a continuing level of operation of the Embassy missions critical functions during all construction periods
  • Closely coordinate all outages with post (weekend outages)
  • Prepare project manuals, bill of materials, quality control plan, construction schedules, construction cost estimates, and verify design/build costs.
  • Compliance with security requirements, CSP.
  • Secure procurement, Warehousing, ISP, secure and non-secure shipping
  • Training, Factory startup and commissioning of new electrical equipment
  • Troubleshooting interface with existing equipment
  • Prepare all required reports
  • Cleanup and Demobilization Project close-out documentation
Specific Trades Self Performed:
  • Project Administration/Management
  • Cost Estimating/Management
  • Design Coordination
  • CPM Schedule
  • Security Requirements
  • Submittals
  • Procurement
  • Shipping Logistics Cost control
  • All on site Management and Labor
  • Carpentry
  • Electrical
  • Mechanical
  • Painting
  • Testing
  • Quality Control
  • Training and Commissioning
  • Project Closeout
Period of Performance

Project award: 2/2015, Actual Completion: 3/2017
Originally Scheduled Completion Date: 3/2016
Government revised completion date: 7/2017

The completion date was extended due to discovery of Asbestos.

Below the hatch in the basement ceiling were 2 building supply and return ducts that blocked the hatch opening. During removal of the ductwork it was discovered to contain asbestos. OBO issued a stop work order while an asbestos remediation team assessed the suspected materials. The install team departed site while the OBO’s remediation team removed the asbestos materials. Upon removal of the asbestos the project resumed.

Project completed on time and within budget.
100% SELF PERFORMED.
Due to the sensitive nature of the project, site plans and drawings are unavailable for presentation.